Crystal Valley Parkway and I-25 interchange is complete

The Crystal Valley Parkway and I-25 interchange, just south of Castle Rock, is fully complete and open as of last month.
Traveling in southern Castle Rock is now a lot easier. Nearly eight months ahead of schedule, the Crystal Valley Parkway and I-25 interchange is fully open as of last month. The project was the Town of Castle Rock’s number one transportation priority and is the largest project of its kind in the Town’s history.
The southbound I-25 on- and off-ramps are open, connecting to the new Crystal Valley Parkway bridge and marking the project’s final major milestone. Other portions of the interchange opened in phases.
The project cost was approximately $144.7 million and was completed within budget, including design, right of way acquisition and construction.
“The early completion of this interchange was achieved through a tremendous effort and collaboration between the Town of Castle Rock, Douglas County, Westside Investment Partners and the entire project team,” stated Tim Maloney, senior vice president at Kraemer North America. “We appreciate the public’s patience as we delivered this key transportation connection for the south end of Castle Rock.”
The primary funding partners for this project include Douglas County, developer contributions and grants from the Denver Regional Council of Governments and the United States Department of Transportation.
Planned since the 1980s, the Crystal Valley Parkway interchange at Exit 179 was designed to improve safety and mobility and provide a key regional connection between I-25, southern Castle Rock and Douglas County. Construction began in 2024.
For more information, visit crgov.com and search “Crystal Valley Interchange.”
Information and rendering by the Town of Castle Rock